"Half the trees you planted on Montrose are dead or severely stressed. What will be different this time?" That question came from a resident during public comment on the West Alabama Street redesign. The Montrose Redevelopment Authority's written answer was one sentence long: "We are planning to use enhanced soil mixes to help with the long-term health for the trees."
The "half" figure is one resident's estimate. No official count has been published. Still, the exchange shows something about the street work across Montrose this fall. Four projects are moving on overlapping timelines, from finished to still in design. Each one makes its own call about how sidewalks, roadway and canopy share the same narrow strip of public right-of-way. The replacement planting on Montrose Boulevard this fall is the first chance to see whether the new trees actually take.
The Montrose Boulevard Improvement Project rebuilt Segment 1, about half a mile from Allen Parkway to just south of West Clay Street. The budget was $17.9 million and the contractor was MC2 Civil. In a year-in-review deck for its July 20, 2026 board meeting, the TIRZ listed the full roadway reconstruction as complete. The deck also lists 10-foot-by-10-foot storm sewers, 5 acre-feet of stormwater detention, and a HAWK pedestrian signal at West Clay.
Most of that work now sits under the pavement. On the surface, the visible piece was always the trees. The plan called for new live oaks next to the mature live oaks being preserved along the roadway. North of West Dallas Street it added cypress, a choice the TIRZ says came out of community engagement as a visual transition to Buffalo Bayou Park. The plan also promised watering and tree replacement for four years after planting.
The cypress were already drawing questions by spring. At the authority's April 20, 2026 board meeting, resident Laura Caille asked about maintenance of certain cypress trees along Montrose. The TIRZ's project page now carries a statement signed by Matt Brollier, chair of the Montrose RDA/TIRZ 27. It says every tree along the corridor has been evaluated, that the contractor "will replace all affected trees this fall, at no cost to the TIRZ or the community, under the terms of the project warranty," and that the maintenance program is being strengthened.
The same page says the streetlights are "progressing towards being turned on." That covers the new City-owned Davit double-luminaire fixtures, which were meant to light the sidewalks along with the roadway. The page is undated, so the best way to check both the replanting and the lighting is to look at the corridor yourself on an evening walk.
If you walk Montrose Boulevard between West Dallas and West Clay, the sidewalk width keeps changing. The design explains why. From Allen Parkway to West Dallas, the east side got an 8-foot sidewalk while the west side kept its existing landscape buffer and mature trees. From West Dallas to West Clay, both sides got 6-foot sidewalks, which narrow to 4 or 5 feet around existing trees to avoid damaging them.
That rule is now the template for the next corridor. In its West Alabama responses, the authority says sidewalks will widen from the 4-foot minimum to 6 feet "wherever feasible," with "localized variations in sidewalk alignment or width" where large, mature trees stand. The same commenter who asked about this pointed to Kipling Street as an example of walks that narrow around trees.
The comment record shows tension over one more material. Another resident argued that structural soil "is just rocks, not soil," holds little water, and might explain why so many Montrose trees are struggling. Staff replied that structural soil "will be used to help prevent damage to sidewalks and road." Taken together, the two answers say West Alabama will use enhanced soil mixes for tree health and structural soil to protect the pavement. The published responses do not say how the two will be combined.
| Project | Limits | Where it stands | What it does for trees |
|---|---|---|---|
| Montrose Boulevard, Segment 1 | Allen Parkway to just south of W. Clay | Roadway listed complete July 2026; warranty tree replacement set for this fall | Live oaks and cypress; four years of watering and replacement |
| Cherryhurst sidewalks | Dunlavy, Fairview, Westheimer, Yupon | Substantially complete Sept. 3; full completion expected mid-October | 5-foot sidewalks built with tree-protection plans |
| Mandell Street | US-59 to Westheimer, about 0.8 mile | Plans resubmitted to the City Aug. 21; construction expected late October or early November | Individualized tree-protection plan along the route |
| West Alabama Street | Shepherd Drive to Spur 527, about 1.6 miles | Design through late 2026; construction early 2027; completion early 2029 | New trees at 30-foot spacing where possible; full inventory pending |
Cherryhurst is the project nearest the finish line. Community Impact reported on September 24 that the sidewalk work was "substantially complete" as of September 3. The contractor is still working through ADA-related and other punch-list items, with full completion expected by mid-October. The project put in new 5-foot sidewalks, wheelchair ramps and driveways inside the blocks bounded by Dunlavy, Fairview, Westheimer and Yupon, generally working one side of a street at a time, with tree-protection plans. The newest reason to walk those blocks sits on Fairview, the street that forms one edge of the project. House of Louie, from chef Justin Yu and bar owner Bobby Heugel, quietly opened at 1931 Fairview for dinner the week of September 30. Its menu draws on French and Italian cooking in a modern American kitchen.
Mandell Street comes next. The project covers about 0.8 mile from US-59 to Westheimer Road. A March 2026 presentation estimated the cost at about $1.5 million. The scope listed in the September update covers:
The March presentation also shows speed cushions on Mandell between Norfolk and Bonnie Brae and new crosswalks at Branard and Sul Ross. Project manager David Greaney said the plans went back to the City on August 21 and were awaiting approval. The late-October or early-November start depends on that approval.
West Alabama is the largest of the four projects by a wide margin. The official August 3 open-house presentation puts construction at $30 million. Earlier reporting in the Houston Chronicle, and an August 25 Community Impact story, cited $28.5 million, with no explanation for the difference. An H-GAC grant of $11,149,937 covers part of the cost, and TIRZ funds cover the rest.
The design fits inside a 60-foot right-of-way: two 11-foot through lanes, an 11-foot two-way center turn lane, and sidewalks on both sides. The plan adds a new signal at Hazard Street and rapid-flashing-beacon crossings at Graustark, Mt. Vernon and Garrott. Underground, the drainage plan adds 5.5 acre-feet of detention. That is slightly more than the 5 acre-feet just built under Montrose Boulevard.
The canopy questions in the design are still open:
Neighbors have pushed hard on the street-level design. Margo Fendrich spoke for Friends of the Boulevard and a coalition of 76 organizations. According to Community Impact, the group asked for more protected crossings, a raised crossing at Dunlavy, refuge islands, and pedestrian-priority signal timing. The current design keeps crossings at 500- to 700-foot intervals and leaves out raised crossings and refuge islands.
The calendar matters here. The comment-response document says major scope changes are no longer considered once the City accepts the Design Concept Report. Smaller, location-specific changes may still be possible. The schedule runs design through late 2026, starts construction in early 2027, and targets completion in early 2029. The authority has promised another public presentation as design advances later this year, but has not set a date.
So the West Alabama tree plan is being finished in the same months the replacement trees go into the ground on Montrose Boulevard. Through 2026, the only evidence anyone has for the "enhanced soil mixes" promise will be the replacement trees on Montrose Boulevard, the ones going in this fall and covered by four years of watering and replacement. The authority's project page for that corridor is where updates are promised.
If you own on one of these four corridors, or you're weighing a home along one, the construction calendar and the planting plan for your block are worth knowing before you make a decision. The team at Beth Wolff Realtors follows Montrose infrastructure work closely, and we're glad to walk through what each project means for a specific address. Request a Personalized Consultation and we'll start with your street.
Stay up to date on the latest real estate trends.
October 8, 2026
October 1, 2026
September 24, 2026
September 17, 2026
September 10, 2026
September 3, 2026
August 27, 2026
August 20, 2026
August 13, 2026