Two houses in Hunters Creek Village closed a month apart this fall. The first, on West Creekside Drive, was built in 1954, has 2,711 square feet on a 15,000-square-foot lot, was listed at $2,000,000 and closed on September 15. The second, on Gawain Lane, was built in 2026, has 4,094 square feet, was listed at $2,800,000 and closed on October 15. At list price, the 1954 house asked about $738 per square foot of living space and the brand-new one asked about $684.
The older, smaller house asked more per foot, and the reason is the ground under both houses. A second set of numbers explains why these two sales are typical of the village: Hunters Creek issues permits for new houses at about the rate homes change hands on the open market.
The City of Hunters Creek Village publishes a building official's report in each monthly council packet. The most recent one, in the October 27, 2026 council packet, shows 16 new-residence permits issued from January through September 2026. The same report puts the full-year totals at 17 new-residence permits in 2024 and 22 in 2025.
On the sales side, Houston Association of Realtors MLS records show 32 single-family closings in the village over the two years ending this November. Thirteen of them closed in 2026.
The two counts don't cover identical periods, but they line up closely. From January 2025 through September 2026, the city permitted 38 new houses. Over a two-year window that roughly overlaps it, 32 homes sold through the MLS. In 2026 alone, the city permitted 16 new houses in nine months, while 13 homes sold through the MLS between January and mid-November.
For a buyer, this means the open market is thin. A village where a house is permitted for every home that sells on the MLS is one where much of the change in housing comes from rebuilding, not from listings. A buyer who watches the MLS for a year here sees about a dozen and a half homes.
New construction is active, but very little of it reaches the MLS as a finished house. Of the 13 homes that closed on the MLS in 2026, two were new builds. The other eleven were built between 1954 and 2010.
| Address | Year built | Living area | List price | Closed |
|---|---|---|---|---|
| 10610 Tarrington Dr | 1961 | 4,706 sq ft | $3,895,000 | Jan. 9 |
| 1006 River Glynn Dr | 2010 | 7,764 sq ft | $3,575,000 | Jan. 23 |
| 412 Timberwilde Ln | 1991 | 9,766 sq ft | $12,250,000 | Feb. 9 |
| 2 Soldiers Creek Cir | 2002 | 7,633 sq ft | $3,300,000 | Feb. 12 |
| 205 Fleetway Dr | 2025 | 8,481 sq ft | $5,999,995 | Feb. 19 |
| 918 Flint River Dr | 2004 | 4,984 sq ft | $4,095,000 | Apr. 1 |
| 8317 Hunters Creek Dr | 2010 | 5,574 sq ft | $2,995,000 | Apr. 30 |
| 620 Hedwig Rd | 1997 | 6,696 sq ft | $4,295,000 | May 1 |
| 10926 Wickwild St | 1961 | 4,718 sq ft | $2,795,000 | May 15 |
| 107 Willowend Dr | 2008 | 8,343 sq ft | $4,500,000 | Jun. 5 |
| 248 Bryn Mawr Cir | 1986 | 6,258 sq ft | $2,460,000 | Jun. 12 |
| 713 W Creekside Dr | 1954 | 2,711 sq ft | $2,000,000 | Sep. 15 |
| 10607 Gawain Ln | 2026 | 4,094 sq ft | $2,800,000 | Oct. 15 |
The MLS reports sold prices here only as ranges, so the table uses list prices. Those list prices undercut any simple rule that newer means more expensive per foot. The two 1961 houses asked very different amounts: Tarrington Drive asked about $828 per square foot and Wickwild Street about $592. The 2025-built house on Fleetway Drive asked about $707, close to what the 1954 house on West Creekside asked. When price per foot of house moves this little with age, buyers are paying mainly for the lot, its frontage and its trees, and the house adds or subtracts from that.
Two sales show the market's range on either side of that land value. 8317 Hunters Creek Drive, built in 2010, was listed at $2,995,000 and closed in a range of $3.32 million to $3.83 million, so the bottom of its sale range was above its asking price. At the top, 412 Timberwilde Lane, a 1991 house on 2.46 acres, was listed at $12,250,000, spent 143 days on the market and closed on February 9 for more than $10 million. A large, well-kept house on a large piece of ground draws buyers even in a village where so many lots are being rebuilt.
The permit count is the start of a build, not the end. The village's 2026 council agendas show how long new houses take to finish here. In January, the council took up extension requests on new-residence permits at 215 Bryn Mawr Circle and 311 Hunters Trail, numbered 202200649 and 202300332. In February, it was 282 Bryn Mawr Circle, permit 202400097. The May agenda listed four: 215 Bryn Mawr Circle again, 502 Thamer Lane, 1121 River Bend Drive and 519 Hunterwood Drive. River Bend Drive was back on the agenda in July. On October 27, the council approved a six-month extension for the new residence at 502 Thamer Lane.
Permit numbers that begin with 2022 and 2023 still appeared on 2026 agendas. A custom house on a Hunters Creek lot can take several years from permit to move-in, and some take longer than planned. The October packet also names Thompson Custom as the primary contractor on a new-residence permit, one of the builders working in the village this year.
This affects the buyer's decision. A finished new house like the one on Gawain Lane or Fleetway Drive is rare on the MLS, appearing about twice a year at the 2026 pace. The rest of the time, a buyer who wants new construction in Hunters Creek is choosing between an older house they can move into now and a lot they would build on over a multiyear schedule. The extension requests show that the schedule can run longer than planned. The older houses in the table are priced largely as land, so their prices already reflect that tradeoff, and the gap between buying an older house and building often turns on time more than on price per foot.
The rebuilding extends to the streets. Reconstruction of Caruthers Lane, Teakwood Lane and Fleetway Drive is underway, with a notice to proceed dated September 1, 2026. The city engineer's report prepared for the October 27 council meeting said crews were starting on roadway panels, beginning with Fleetway and moving to the other two streets after. Fleetway Drive is also where one of this year's two new-build sales closed, in February. A buyer touring that part of the village this winter will see road crews outside, and the newly built houses on those streets will have new pavement when the work is finished.
For a buyer comparing Hunters Creek with the other Memorial Villages, the Piney Point Village lot-size guide covers the same questions about land and building potential for the next village over. Owners getting ready to put an older house on this thin market can see how we approach presentation in Getting an Older Hunters Creek Village Home Market-Ready.
How many homes come up for sale in Hunters Creek Village in a year? On the MLS, 13 homes closed from January through mid-November 2026, and 32 closed over the past two years. The city permitted 22 new houses in 2025 and 16 in the first nine months of 2026.
Are older houses here priced lower per square foot than new ones? Not reliably. In 2026 closings, list prices per square foot for houses from the 1950s and 1960s ranged from about $592 to about $828. The two new builds that closed asked about $684 and about $707.
Where can I follow new construction in the village month by month? Each monthly council packet on the City of Hunters Creek Village website includes the building official's permit report, with new-residence permits counted by month.
A thin market like this one is easier to judge with someone who reads the permit reports and the closings together. If you are weighing an older Hunters Creek house against a lot and a build schedule, or deciding when to list a home here, Beth Wolff Realtors can walk through the recent sales on your street and what they mean for your timing. Request a Personalized Consultation, or start with a home valuation.
Stay up to date on the latest real estate trends.
November 26, 2026
November 19, 2026
November 12, 2026
November 5, 2026
October 29, 2026
October 22, 2026
October 15, 2026
October 8, 2026
October 1, 2026